C2089 Sahakol Mae Moh 8 FLSmidth Conveyor System

6 ratings | 796 views
FLSmidth Conveyor System for Sahakol Equipment Public Company Limited’s Mae Moh Overburden Removal Phase 8 project. Largest conveyor in Thailand. Conveyor System Data: 12 Conveyors Belt Width 2200 mm and 2600 mm. Capacity 27.600 t/h. 12.6 km length. Drop -120 m, Lift +310 m. 40 Conveyor Drives 1750 kW and 2000 kW. Total Weight 10.000 tons. Total installed power 72 MW. 105 km Cables. 1000 Field Devices. 9000 PLC Inputs and Outputs. Milestones: Sahakol-FLSmidth Contract Signing: 18 November 2016 Start of Operation: 1 March 2018 Restart of Operation: 21 June 018 after landslide. Hand Over Ceremony: 2 August 2018 Project Manager: Helmut Oberrisser, FLSmidth Video by Helmut Oberrisser